Timeline and next steps
Anticipated timeline
We are currently in the pre-application stage of the project, which is when we do early design work. This includes completing environmental studies, developing initial proposals, and engaging with local communities.
Stage one public consultation ran from 6 May to 30 June 2026. A second round of consultation on more detailed proposals is planned for late 2026 / early 2027, ahead of submitting the application in mid-2027.
Our current anticipated timeline is outlined below.
Summer 2025
Initial planning work on the project
Spring 2026
Stage One Consultation and Scoping Submission
Late 2026 / Early 2027
Stage Two Consultation
Mid 2027
DCO submission
Autumn 2028
Examination
2029
Recommendation and decision